Finding

The UK had 124,738 public EV chargers on 1 October 2026, with 3,567 added between 1 July and 1 October 2026 (Whito calculation from Department for Transport statistics published 25 November 2026).

Source: Whito, whito.co.uk/renewable-installers/uk-ev-charger-installation-data, 2026-11-25. Free to quote with a link to this page.

By · Published

The UK had 124,738 public EV chargers on 1 October 2026, according to Department for Transport (DfT) statistics published on 25 November 2026. That is 180.0 public chargers for every 100,000 people. This page sets out the numbers EV charger installers and their customers ask about most, each with its date and source.

Key figures

  • 124,738 public EV chargers in the UK on 1 October 2026 (DfT).
  • 29,772 of them were rated rapid or above, 50kW and faster (DfT). That is about 24% of all public chargers.
  • 8,686 public chargers were added in 2026 up to 1 October, against 13,281 in the whole of 2025 (DfT).
  • 3,567 were added between 1 July and 1 October 2026 (Whito calculation from DfT’s 121,171 on 1 July and 124,738 on 1 October).
  • 8,166 home charging installations were funded by government grants in the 12 months to 1 October 2026, and 11,517 workplace installations (DfT).
  • There was one public EV charger for every 18 battery electric vehicles on 1 July 2026, the latest date DfT has vehicle figures for.

Public EV chargers in the UK

MeasureFigureDate
Public EV chargers124,7381 October 2026
Public EV chargers per 100,000 people180.01 October 2026
Rapid or above (50kW+)29,7721 October 2026
Rapid or above per 100,000 people42.91 October 2026
Rapid or above within one mile of England’s motorways and major A-roads9,6161 October 2026
Public EV chargers121,1711 July 2026
Added in 2026 so far8,686To 1 October 2026
Added in 202513,281Calendar year 2025

Source: DfT, Public electric vehicle charging infrastructure statistics: 1 October 2026, published 25 November 2026. Data collated by Zapmap from charge point operators. These are official statistics in development.

Is the public network growing more slowly?

On DfT’s figures, 8,686 public chargers were added in the first nine months of 2026, an average of about 965 a month. In 2025 the network grew by 13,281, about 1,107 a month (Whito calculations). There is a caveat: DfT’s July release said one operator removed about 1,270 chargers from its data in June 2026, which pulls the 2026 figure down. Without that removal, the 2026 pace would be close to 2025’s.

Our reading: the public network is still growing by several thousand chargers a quarter. The numbers do not support a claim that growth has collapsed or that it has sped up.

Chargers by speed

Power bandDfT labelShare of public chargers
3kW to under 8kWStandard49%
8kW to under 50kWStandard plus27%
50kW to under 150kWRapid12%
150kW and aboveUltra-rapid12%

Source: DfT, 1 October 2026. Percentages may not sum to 100 because of rounding.

Where the chargers are

DfT says London has many more public chargers per person than the rest of the UK, but the second-lowest number of rapid or faster chargers per person, because most London chargers are standard on-street units. Provision was typically above average in Scotland, Wales and Greater London on 1 October 2026.

By location type, 52% of public chargers were at destinations such as car parks, 33% on residential streets, 11% en route such as motorway services, and 4% semi-public, such as workplace car parks (DfT, 1 October 2026).

In England and Wales, 16.8% of public chargers were in rural areas, where 17.5% of people live (DfT, 1 October 2026).

Grant-funded home and workplace chargers

Grant schemeTotal fundedIn the 12 months to 1 October 2026
All home charging grant schemes (since 2013)413,420 installations8,166
Chargepoint grant for renters and flat owners27,208 sockets (£9.6 million)6,869
Chargepoint grant for residential landlords1,919 sockets (£677,483)316
All workplace charging grant schemes (since 2016)88,145 installations11,517
Public charging grant schemes (since 2017, provisional)25,858 EV chargersn/a

Source: DfT, Grant schemes for electric vehicle charging infrastructure statistics: 1 October 2026, published 25 November 2026. Home scheme totals count installations and the individual schemes count sockets, so the rows do not add up.

Search interest in EV charger installation

On Google Trends, UK interest in “ev charger installation” in the week of 22 November 2026 was 70 on its relative scale, against 47 in the same week of 2025. It peaked in April 2026. Scotland showed the highest interest of the four UK nations. The related search rising fastest was “uk ev charger installation data”, up 400% (Google Trends, UK, past 12 months, checked 25 November 2026). Trends figures are relative, not search counts.

What this means for an EV charger installer

  • Start: say which grants your customers may qualify for. The renters and flat owners grant funded 6,869 sockets in the 12 months to 1 October 2026, more than any other home scheme DfT reports.
  • Build: workplace grants funded 11,517 installations in the same 12 months. A page for employers and landlords answers a different buyer from a page for homeowners.
  • Scale: keep your figures dated. DfT publishes every quarter, and the next release is due in February 2027.

How we did it

  • Sources: the two DfT reports in the Electric vehicle charging infrastructure statistics: 1 October 2026 release, read on 25 November 2026, plus the 1 July 2026 release for the earlier total and the data note on the June 2026 removal.
  • Whito calculations: chargers added between 1 July and 1 October 2026 (124,738 minus 121,171), monthly averages for 2025 and 2026, and the rapid share (29,772 of 124,738).
  • Limits: DfT labels these official statistics in development, and its figures can be revised. Home charging installed without a grant is not counted in the grant figures.

Related Whito pages

Cite this page

Whito (2026). UK EV charger installation data, from DfT statistics published 25 November 2026. https://whito.co.uk/renewable-installers/uk-ev-charger-installation-data/

Common questions

How many public EV chargers are there in the UK?

124,738 on 1 October 2026, according to Department for Transport statistics published on 25 November 2026.

How many EV chargers were installed in the UK in 2026?

8,686 public EV chargers were added between 1 January and 1 October 2026 (DfT). Grant schemes also funded 8,166 home and 11,517 workplace installations in the 12 months to 1 October 2026.

How many rapid chargers are there in the UK?

29,772 public chargers rated 50kW or above on 1 October 2026, about 24% of the total (DfT).

How to read this study

The figures show what Whito found in the sample and on the dates stated on this page. They describe the businesses, prices or answers we looked at, not every UK business. Prices and AI answers change over time. Every Whito study follows our research methodology standard. Spotted an error? Tell us and we will check it.

Whito logo
Jacob Whitmore
Whito is an independent UK research publisher. We publish research on how UK businesses are found, trusted and priced: what they cost to market, how their sectors work, and who actually gets recommended. Studies are free to read, every figure carries the date it was checked, and nobody pays to appear.